The planning cycle
An operational period is the time set for carrying out one set of objectives, as written in the Incident Action Plan. Each period gets its own objectives, assignments and briefing. The plan for the next period is written during the current one.
Setting the period length
Start with 12-hour periods during active containment, so each shift has its own plan and briefing. Move to 24 hours once eradication and recovery are routine, and to longer periods for monitoring. The Incident Commander sets the length, and it goes in the IAP.
Writing objectives
An objective names an outcome, a measure and a time. It says what must be true, and leaves how to the tactics meeting.
Example
| Weak | Stronger |
|---|---|
| Contain the ransomware | No new encryption events on any host after 14:00 Tuesday, confirmed in EDR telemetry |
| Reset passwords | Every account in the compromised group reset, with sessions and tokens revoked, by 18:00 |
| Find out what happened | Scope confirmed for the finance tenant, every affected host and account listed with evidence, by 09:00 Wednesday |
| Keep leadership informed | Status summary to the executive group at 09:00 and 17:00 each day until recovery is complete |
The meetings
| Step | Who | Produces |
|---|---|---|
| Initial response and assessment | First responders | Size-up and first actions |
| Incident briefing | Outgoing and incoming command | ICS 201 |
| Initial unified command meeting, if used | Unified command members | Agreed objectives, one organization and one Operations Section Chief |
| Objectives meeting | IC or unified command | Objectives for the next period (ICS 202) |
| Command and General Staff meeting | IC with Command and General Staff | Priorities, constraints, decisions |
| Tactics meeting | Operations, Planning, Logistics, Safety | Work assignments and resource needs |
| Planning meeting | Command and General Staff | Agreement to the plan |
| IAP preparation and approval | Planning prepares, IC signs | The Incident Action Plan |
| Operations briefing | The oncoming shift | Assignments delivered. The period starts |
| Execute and assess | Operations, with Planning tracking | Status updates, changes flagged to command |
Meeting agendas
The Planning Section Chief runs every meeting except the objectives meeting, which the Incident Commander runs. The lengths are starting points. Keep each meeting to its agenda and move side discussions out of the room.
Scripts for opening the objectives meeting and the operations briefing are on Command and handover.
| Meeting | Facilitator | Length | Agenda |
|---|---|---|---|
| Objectives meeting | Incident Commander | 20 minutes | Review progress against the current objectives. Set up to three objectives for the next period, each with an outcome, a measure and a time. Set command emphasis and the period length. Decide what goes to executives. |
| Command and General Staff meeting | Planning Section Chief | 30 minutes | Incident Commander presents the objectives and emphasis. Each section and Command Staff member raises constraints, needs and decisions. Incident Commander decides or takes items to the executive group. |
| Tactics meeting | Planning Section Chief | 45 minutes | Operations proposes groups and tasks for each objective. Planning checks them against scope. Logistics confirms people, tools and access. Safety reviews risk to people and physical processes. The result is an ICS 215 worksheet, the Safety Officer's ICS 215A and the resource orders. |
| Planning meeting | Planning Section Chief | 30 minutes | Situation briefing. Operations presents the plan. Each section confirms it can support it. Incident Commander approves the plan in principle and sets the IAP deadline. |
| Operations briefing | Planning Section Chief | 20 to 30 minutes | Roll call and the period. Incident Commander gives command emphasis. Situation and objectives. Operations delivers each group's assignment. Logistics gives the communications plan. Safety message. Public Information and Liaison notes. Incident Commander closes and the period starts. |
A filled-in plan for one period is in the worked example.
A day in 12-hour periods
Example
| Time | What happens |
|---|---|
| 06:30 | Operations briefing for the day shift |
| 07:00 | Day period starts. Night shift hands over and goes to rest |
| 09:00 | Executive update from the status summary |
| 11:00 | Objectives meeting for the night period |
| 12:00 | Command and General Staff meeting |
| 13:00 | Tactics meeting |
| 14:30 | Planning meeting |
| 16:00 | IAP signed |
| 17:00 | Executive update |
| 18:30 | Operations briefing for the night shift |
| 19:00 | Night period starts. Day shift hands over and goes to rest |
| 23:00 | Objectives meeting for the next day period, run by the night Incident Commander |
| 00:00 | Command and General Staff meeting |
| 01:00 | Tactics meeting |
| 02:30 | Planning meeting |
| 04:00 | IAP signed. It is briefed at 06:30 |
Each shift plans the other shift's period. Once the incident settles, switch to one 24-hour plan with a briefing at each shift change, and the night cycle drops away.
Schedule for your period
Set when the next operational period starts and how long it runs. The schedule places each meeting of the cycle before that start, using the spacing of the 12-hour example above. Move any meeting to fit the incident.
What goes in the IAP
- Objectives and command emphasis (ICS 202)
- Organization assignment list (ICS 203) or chart (ICS 207)
- Assignment lists, one per group or division (ICS 204)
- Communications plan (ICS 205)
- Safety message (ICS 208)
- Current situation summary
For Type 4 and 5 incidents the incident briefing (ICS 201) is the plan.