2Respond and manage

Extended incidents

Ransomware recovery, a breach with notices to send, and a plant restart under engineering validation can each run for weeks. The organization built for the first night wears out by the second week.

This page covers the change from hours to weeks: working limits, rotating command, a slower cycle, a smaller organization, and a record that survives every handover. Shift-to-shift mechanics are on Command and handover and The planning cycle.

Working limits

Set these in policy as part of preparing, and give the Safety Officer authority to enforce them. The values are starting points.

LimitStarting point
Operational period12 hours while containment is active. 24 hours once recovery is routine
Time on duty in one shift13 hours at most, including briefing and handover
Longest shift16 hours, approved by the Incident Commander and logged with the reason
Rest between shiftsAt least 11 hours off duty. Travel counts as duty
Days offFrom the second week, at least 36 hours clear of duty in every 7 days
Time on the incident14 days, then 3 days off before any further incident duty

The A, B, C rotation in the staffing math meets the rest rule. From the second week, give each person their 36 hours by adding a relief for one shift, or by moving to 24-hour periods with a smaller night crew.

These limits sit inside the wildland fire standards in NWCG PMS 902, May 2025 edition. NWCG lists it as current in October 2026; the limits below were checked September 2026. PMS 902 sets a minimum 2:1 work-to-rest ratio, counting travel as work. It treats shifts over 16 hours as the exception, justified by the Incident Commander or Agency Administrator in the daily records, and allows none over 24 hours. Its standard assignment is 14 days, followed by 3 mandatory days off, with an extension of up to 14 more days and 2 days off before the 22nd day.

Fatigue

Supervisors watch for these signs in every shift and report them to the Safety Officer:

  • Errors in routine work: the wrong host, a typo in a command, a ticket closed early
  • Repeated questions on the bridge, and slower answers
  • Items missed at handover
  • Short tempers and arguments over small points
  • Nodding off, or long stretches without a break or a meal
  • Someone refusing relief because nobody else knows their part
#ItemOwner
1Hours on duty and last-slept times checked on the ICS 211 each periodSafety Officer
2Anyone past the duty limit relieved, after a handoverSafety Officer
3Any destructive or irreversible change by someone past 10 hours on duty checked by a second personOperations
4Anyone nobody else can relieve paired with a relief this period, and their knowledge written downPlanning
5A ride home arranged for anyone too tired to driveLogistics
6Names at or near the limits, and the actions taken, put in the safety message and the handoverSafety Officer

Rotating the Incident Commander

Command changes at each shift by transfer. Over weeks, the command team rotates as well. Bring in a fresh team, meaning an Incident Commander, a deputy and section chiefs, when any of these is true:

  • The current team reaches 14 days on the incident.
  • The incident will run at least two more weeks.
  • The main effort changes, such as from containment to notification and litigation.
  • Update times or objectives slip for two periods in a row.
  • The Safety Officer reports that the team cannot be relieved inside the limits.

The incoming team shadows for one full operational period and takes command at the start of the next. It is briefed from the current IAP, the ICS 209, the decision register and the open action tracker.

Change the Planning Section Chief one period after the Incident Commander, so someone in command saw both teams. The outgoing Incident Commander stays reachable for a week. The Documentation unit leader stays through the change.

Battle rhythm

Slow the cycle as the work settles. The Incident Commander sets the period length in the IAP, and each change is an entry in the decision register.

StagePeriodPlanning cycleICS 209Move on when
Active containment12 hoursA full cycle each period, each shift planning the other'sEach period, and before each executive updateNo new scope for two periods, and containment is intact
Recovery24 hoursOne cycle a day, with an operations briefing at each shift changeDailyCritical services restored and eradication verified
Long tail1 weekObjectives and planning meetings weekly, tactics as neededWeekly, and at any change in scope or impactThe demobilization plan closes the incident

The long-tail organization

Weeks two to six are rebuilds on a schedule, monitoring, notices, claims, regulator questions and legal holds. Run them with a smaller organization on business hours.

SeatWeeks two to six
Incident CommanderOne named Incident Commander on business hours, with a named backup
OperationsA recovery group on the rebuild schedule, and a monitoring group watching for the attacker's return
PlanningThe timeline, the decision register, the open action tracker and the demobilization plan
Legal advisorNotices, regulator questions, legal holds
Public Information OfficerNotices to people and customers, call center scripts, media
LiaisonThe insurer, law enforcement, suppliers, and regulators through counsel
Finance/AdminClaims, invoices, the cost summary

Fold Logistics into Planning once temporary access and loaned hardware are closed out. Fold Intelligence/Investigations into Operations once the forensic report is final, unless law enforcement or litigation still needs it.

Close the Safety Officer seat once nobody works outside business hours and no work touches a physical process. Release people through the demobilization check-out.

One record across rotations

  • One incident record, one timeline, one decision register and one open action tracker for the whole incident. Numbering continues across teams.
  • Each incoming Incident Commander reads the open entries in the decision register before taking command.
  • A decision stands until a new entry reverses it and names the new facts that justify the change.
  • Corrections are new entries. The earlier entry stays, marked as replaced.
  • Board, regulator and customer reports come from the same record, as in board and government reporting.

Stepping down executive and board updates

The update schedule sets the cadence while the incident is active. Stepping it down is an executive group decision, entered in the register, once impact has stopped growing and recovery runs to plan. Announce each change in the update before it takes effect, with the time of the next update.

StageExecutivesBoard
Active containmentAs the severity sets. For SEV 1, every 30 minutes until mitigated, then every 2 hoursThe same day, then daily
RecoveryTwice a day at fixed timesDaily, or as the executive sponsor sets
Long tailWeekly, and at once on any change in scope or impact, or any notice sentAt each scheduled meeting, with a written update when a notice goes out or a regulator acts

Planning starts the demobilization plan as soon as the long tail begins.

Adapted from the National Incident Management System, Third Edition (FEMA, 2017). Cyber adaptation, examples and templates by Habib Tora, licensed under CC BY 4.0. Not published by, endorsed by, or affiliated with FEMA or the Department of Homeland Security. Structure after Google's SRE Incident Management Guide. Companion to PIVTR-D.