Demobilization releases people and resources in order, and closes out access, evidence custody and hours for every person. Planning writes the demobilization plan as soon as the end is in sight, and the IC approves it.

NIMS sets its goal as the orderly, safe and efficient return of each resource to its original location and status.

Exit criteria

The Incident Commander ends the incident when every item below is met and recorded.

#ItemOwner
1Each objective met, or moved to the remediation project by a recorded decisionIncident Commander
2Technical closure signed on PIVTR-D T5, with the monitoring kept and its end dateOperations
3Residual risks accepted by the risk owner on PIVTR-D T6, with the conditions that would reopen the incidentIncident Commander
4Restored systems accepted by their owners and running normallyOperations
5Every notification made, or assigned to a named owner with its deadlineLegal advisor
6Every open action and outside commitment closed, or given an owner outside the incidentPlanning
7Closeout meeting completed with the executive who delegated authority: lasting consequences, unfinished records, their concernsIncident Commander

Work that outlasts the incident becomes a remediation project, run through normal project and change management. Before the stand-down, record three things: an owner who has accepted the work, a backlog, and a first review date at the incident review board.

The backlog gives each item a priority and a source such as a T6 compensating control. Work without an owner stays in the incident.

Stepping down

  • Fold a section back when the person above it can carry its remaining work for a full operational period.
  • Make each change at the start of an operational period, and write it in the IAP.
  • Keep Planning until the records are consolidated, Liaison until every outside commitment is closed, and Finance/Admin until final invoices are requested.
  • At Type 4 the ICS 201 is the plan again.
  • Handing back from a larger or outside team is a transfer of command. In FEMA's ICS 300 course, the type is reduced, with any transfer of command, when the Agency Administrator agrees.

The Incident Commander announces each change on the command bridge and in the next status summary, naming who now carries each folded duty.

Release order

Release outside responders and borrowed staff as their objectives close. Keep core responders until eradication is verified. Keep monitoring capacity after that, at the level the recovery plan calls for.

Check-out, per person (after ICS 221)

#Item
1Assignment handed to a named person, or closed
2Activity log submitted to Documentation
3Notes, evidence and media handed over, with custody recorded
4Temporary accounts, access and tokens revoked
5Loaner hardware and licenses returned
6Hours submitted to Finance/Admin
7Rest before the next shift or return to normal duty

Closing the incident organization

#Item
1IC declares the end of the incident, with the time
2Final status summary issued
3Emergency changes reviewed and closed or made permanent
4Outside engagements ended in writing and final invoices requested
5Records consolidated by Documentation and indexed
6Costs totaled by Finance/Admin, insurer's claim file updated
7After-action review scheduled, run as the PIVTR-D debrief

Writing the plan

One plan covers the incident, adapted from the sections of the ICS demobilization plan. Each person's release goes on an ICS 221, and each decision to keep a containment measure goes in the decision register.

Demobilization plan

DEMOBILIZATION PLAN
Incident name and number:
Date:                             Prepared by (Planning):
Exit criteria met, with the record for each:
  Objectives met or moved:
  Technical closure (T5):
  Residual risk accepted (T6):
  Notifications made or assigned:
  Open actions and commitments assigned:
Resources to release, in order:
  #   Resource or group   Release after   Released by   ICS 221 done
What stays, and until when:
  Monitoring (rules, watch list, alert route):         until:
  On-call contact:                                       until:
  Containment measures kept, by recorded decision:
Records to file, and where:
  Activity logs, IAPs, decision register, evidence register,
  final ICS 209, T5, T6:
Handoff:
  Remediation project:
  Owner:                            Backlog at:
  First review date:
Stand-down announcement (date, time, time zone):
Approved by (Incident Commander):                 Date, time:
Accepted by (remediation owner):                  Date, time:
Agreed by (Agency Administrator):                 Date, time:

Standing down

The Incident Commander reads the stand-down on the command bridge at the planned time, then posts it in the incident channel and the final status summary.

Script for announcing the stand-down

This is [name], Incident Commander for [incident name]. As of
[time and time zone], the incident is closed and the incident
organization stands down. The exit criteria are met and signed.
[Owner name] owns the remaining work as [project name], with a
first review on [date]. Monitoring continues until [date]. Report
any new sign of this incident to [on-call contact], who can reopen
it. Submit activity logs and hours by [time]. The after-action
review is on [date].

Retained monitoring

  • Detection rules written during the incident stay enabled, and their alerts reach the on-call team tagged with the incident name.
  • A named analyst checks a daily watch list of the accounts, hosts, indicators and third-party connections from scope, with the T6 conditions that would reopen the incident beside it.
  • The end date is set at closure. Start with 30 days, and 90 where the attacker had privileged access. On that date the owner ends the monitoring, extends it once, or makes the rules permanent detection content.

Responder recovery

  • Anyone who worked past the maximum shift length, or more days in a row than the agreed limit, takes at least one full day off before normal duty. Their manager protects it.
  • Each manager runs a one-to-one check-in with each responder within a week of release: sleep, workload, anything that still weighs on them, and where to get support, such as the employee assistance program.
  • Compensatory time or pay follows HR policy, from the hours Finance/Admin recorded.

Built from NIMS, third edition (October 2017), and FEMA's ICS 300 course, Unit 7, for the plan's sections, the closeout meeting and reducing the type. The exit criteria, step-down rules, plan layout, script, monitoring and recovery steps are additions to this guide.

Adapted from the National Incident Management System, Third Edition (FEMA, 2017). Cyber adaptation, examples and templates by Habib Tora, licensed under CC BY 4.0. Not published by, endorsed by, or affiliated with FEMA or the Department of Homeland Security. Structure after Google's SRE Incident Management Guide. Companion to PIVTR-D.